BOA SUB C

  • Type: OCV
  • Built: 2007
  • Class: DNV-GL +A1 EO Tug HELDK Dynpos AUTRO CLEAN Comf-V(3) Comf-C(3) register notations dk(+) hl(p) TMON
  • Deck Space: 2,004 m2
  • AHC Crane: 400 t AHC/ 30 t AHC auxiliary crane to 3000m/ Carousel 2,500 t
  • AH/Towing Winches: 600 t/ 500 t/ 500 t to 3000m
  • Bollard Pull: 220 t
  • ROV Operations: 2 x Oceaneering Millennium Plus in hangars to 3,000 m
  • Accommodation: 153 beds
  • test: test
Download Specification

REFERENCES

CHARTERER
WORK
PERIOD
Adwen
W2W and Accommodation Services
January 2019- Ongoing
Adwen
W2W and Accommodation Services
April 2018- October 2018
Adwen
W2W and Accommodation Services
May - September 2017
Boskalis
Subsea Intallations, Construction and ROV inspections
January - February 2017
Technip
Decommissioning of Blind Faith 2 Field
October- December 2016
ExxonMobil
Julia Phase I Installation: Pump Module recovery and Dummy Pump Module Installation
September- October 2016
Technip
Flowline pre-commissioning
August-September 2016
Technip
Odd Jobb Well site: Subsea and Survey Operations
August 2016
Boskalis
Installation of FPSO mooring legs
May- June 2016
EMAS
Replacing old mooring chains and risers for FSO unit and associated CALM Buoy
March- April 2016
FASL
Subsea Installations, Construction and ROV inspections
January- February 2016
Statoil
FSU Mooring and STL Buoy installation
August- September 2015
Bumiarmada
STP Buoy and Mooring installation
June- August 2015
Statoil
Template structures and Suction Anchor Installation
April-May 2015
Statoil
Installation of flexible flowlines and jumpers, spools, PLETs, pig launchers and receivers, installation of template structure, installation of manifold, installation and replacement of umbilicals. I
2014-2015
Statoil
Installation of wire segments and MLBEs; disconnection and retrieval of Clump Weight (CW); installation of Transponders; performing as-installed survey.
August 2014
Statoil
Suction anchors and mooring chain/wire installation
July- August 2014
Statoil
Spool installation; Installation with the rail system
July 2014
Statoil
Transportation and Mooring Installation. Removal of old STL- loading buoy, recovery of 8 hooking lines, anchors and HLBE’s; Laydown of riser on seabed
June 2014
Dong Energy
Dolwin Alpha HVAC Offshore Cable Installation. Installation of two HVAC cables between the Borkum Riffgrund platform and the DolWin Alpha platform
May-June 2014
Statoil
2/4-S Tripod and Jacket structures removal
April-May 2014
Apache
The marine installation of Subsea Isolation Valve (SSIV) and wetstore of 2x36inch spool pieces on the Forties Charlie SSIV Retrofit Project
April 2014
MODEC
Replacement of the top chains on all eight mooring lines; replacement of polyester ropes on mooring lines number 6 and number 7
March 2014
MODEC
ROV survey, chain recovery, preliminary repair of mooring system on MV10 Baobab; temporary repairs on the mooring line number 6 and 7 (top chains broken and lying down on the seabed), top chain replaced by the new one
January- February 2014
Premier Oil
Development of the Dua subsea field as a subsea tieback to the existing Lewek Emas FPSO (Chim Sao Field); Subsea Structures, Risers and Umbilical Installation
August- September 2013
Santos
Task- repair works on the Mutineer field; Survey - in field testing and troubleshooting; deployment of new jumpers as dictated by testing outcomes, installation of grout bags on new jumpers
August 2013
Apache
Development of Coniston and Novara oilfields via a tie-back to the existing Van Gogh field and Ningaloo Vision FPSO
May-August 2013
Noble Energy
Subsea field development including main and infield umbilical installation, subsea structures and foundations installation, rigid subsea jumper installation, flying leads and flexible jumper installation
August 2012- February 2013
BP
Jumper recovery/remediation, deployment and connection; Manifold installation/flushing, pigging operations; SFL change-out and installation of long term intervention caps
January- July 2012
BP
Pre-set and abandonment of the twelve mooring lines (chain and polyester rope pattern) on the sea floor. The pre-set mooring lines will ultimately be recovered individually and handed over to the FPSO for hook-up and final tensioning.
December 2011
Hess
Freespan remediation on existing Ceiba Rigid Flowlines that were discovered to have anomalous span length. The remediation was done with use of Mechanical Support Stands, Pipe Lift Frames and SlingBags with sand bags.
September- October 2011
BW Offshore
Mooring Line Rectification; Mooring Lines Survey; Mooring Lines Stretching Operations; Depth Surveys and Line integrity Survey of Stretched Lines; Survey of all mooring lines connected with the FPSO BW Pioneer
June 2011
BW Offshore
Emergency intervention at Cascade-Chinook field
March-May 2011
Shell
Load out, lay and connection of 38km service Umbilical between Shell Cougar platform and Popeye Drill Centre; Installations of Subsea Distribution Hardware (SDH) -EFL and HFLs; Mattress installation over pipeline and umbilical crossings
February 2011
Petrobras
Discovery pipeline system valve repair operations. Cascade&Chinook gas export jumper installations.
June- July 2010
BP
Jumper deployment and installation; DC-41 Manifold recovery operations; SFL and EFL deployment and installation; Deployment and installation of pigging loop; Recovery of CAT tools and Connection shroud installations
May-June 2010
BP
Long term operations for BP Macondo disaster recovery. BOP (Blowout Preventer) intervention and installation of overshots; ROV tooling and removal of BOP equipment; Installation of flexible flowlines for choke and kill operations; Debris clearance; Valve operational and preparations for recovery of BOP and drill string; Various monitoring and inspection operations
April- September 2010
BP
Jumper recovery, deployment and connection; Manifold flushing and pigging operations; SFL change-out and installation of long term intervention caps
January-April 2010
ENI
Repair of inter-platform power cables between Kitina and Foukanda platforms; Service umbilical lay and connection between Kitina platform and Djambala 7 well; Power cable lay between Loango and Zatchi platforms
December 2009
BP
Jumper, HFL and SFL installations; Manifold deployment
August-September 2009
Statoil
Installation of 16-point mooring system for Gjøa semi-submersible platform comprising 130t suction anchors and composite chain/wire/chain mooring lines
May-June 2009
BP
Installation of 12-point mooring system and hook-up of Thunder Hawk semi-submersible platform
March-April 2009
BP
Jumper recovery and re-installation
January-February 2009
Enbridge
Gas export jumper installation to Shenzi gas export line
December-January 2009
BP
Manifold suction piles installation; jumper installation
October-December 2008
BHP Billiton
Umbilical installation
September-October 2008
SBM Offshore
Driven anchor pile installation in 1800 m of water
July-August 2008
Chevron
Installation of subsea components and umbilical in water depth 2000
July 2008
BP
Jumper and subsea installation
May 2008
Chevron
Installation of 8-point mooring system for the Blind Faith platform comprising of composite chain/polyester/chain mooring lines; Hook-up of mooring lines to Blind Faith semi-submersible platform; Recovery and connection of pre- deployed risers from seabed to the platform
March-July 2008
Anadarko
Jumper and subsea installations
February 2008
Chevron
Suction piles installation; Jumper installation
October-November 2007
BP
Subsea Installations
October 2007